The verdict in three sentences
A B2B brochure site typically ships in 6 to 10 weeks; a content-rich institutional site in 10 to 16 weeks. The critical path is almost never development but content and mockup sign-off on the client side. Book your agency slot 4 to 6 weeks before your desired kickoff, especially if you are chasing a non-negotiable trade-show date.
The typical brochure-site plan (London, 2026)
Here is the realistic phase breakdown. Content is produced in parallel with design/build so it never lengthens the critical path.
| Phase | Duration | Deliverable | Who signs off |
|---|---|---|---|
| Discovery | 1 wk | Site map, brief | Leadership |
| UX / wireframes | 1-2 wk | Zoning, journeys | Marketing |
| UI design | 2-3 wk | Approved mockups | Leadership + marketing |
| Build / dev | 2-3 wk | Site on staging | Project manager |
| Content | 1-2 wk (parallel) | Copy, visuals, SEO | Marketing |
| QA & launch | 1 wk | Site in production | Everyone |
| Total brochure | 6-10 wk |
Institutional: same skeleton, stretched
| Phase | Brochure | Institutional |
|---|---|---|
| Discovery | 1 wk | 2 wk |
| UX / wireframes | 1-2 wk | 2-3 wk |
| Design | 2-3 wk | 3-4 wk |
| Build | 2-3 wk | 3-5 wk |
| QA | 1 wk | 1-2 wk |
| Total | 6-10 wk | 10-16 wk |
The slippage factors (and their cost in weeks)
Timelines slip for predictable reasons. Price them in from the start:
- Content not ready: +2 weeks on average. The number-one cause of delay.
- Mid-project scope additions: +15 to 30% (an added e-commerce page, a configurator...).
- Long approval cycles: each unplanned mockup round costs 3 to 5 days.
- Third-party integrations (CRM, booking): +1 to 2 weeks if access arrives late.
- Translations: +1 week per extra language.
A 15% buffer on the total and a scope freeze after mockup sign-off are the two levers that save a trade-show date.
Mini case study
Sarah, COO of a manufacturing SME in London (32 staff), wants an 8-page brochure site live before a 15 October show. Counting backward: QA 1 week, build 3 weeks, design 3 weeks, UX 2 weeks, discovery 1 week, so 10 weeks + 15% buffer = 11.5 weeks. She must sign by late July. By preparing content during discovery (instead of waiting for the build), she saves the classic +2 weeks and hits the date with 5 days to spare. Cost of the avoided delay: a missed show is worth tens of thousands in lost pipeline.
Need a professional website?
Kolonell builds websites that attract clients, optimized for the Sénégalese market. Free quote in 2 minutes.
FAQ
How long for a B2B brochure site?
Between 6 and 10 weeks for 5 to 10 pages. A 3-week express build exists but sacrifices bespoke UX and SEO depth.
Why does my project take longer than planned?
In 60% of cases it is client content (copy, photos, approvals) that is not ready. Development is rarely the bottleneck.
When should I contact the agency before a show?
At least 4 to 6 weeks before your desired kickoff, because good agencies have a backlog. For an October show, start the consultation in June or July.
Can content be produced in parallel?
Yes, and it is recommended: preparing copy and visuals during design avoids adding 2 weeks to the critical path. Include a content workstream if your teams are stretched.
How do I secure a non-negotiable date?
Freeze scope after mockup sign-off, add a 15% buffer, and book approval slots in calendars ahead of time.
Let's scope your project. Tell us your target date (show, launch), page count and integrations: we build a realistic reverse plan with buffer. Detailed quote within 48 h. WhatsApp +221 77 596 93 33.