The verdict in three sentences

A serious B2B brochure site ships in 7 to 11 calendar weeks, not three. The main bottleneck is not the code but content delivery and review cycles on the client side, responsible on average for +4 weeks of delay. Locking a firm launch date requires a 1-to-2-week buffer and contractual review SLAs.

What is the realistic phase-by-phase plan?

Each phase has an irreducible duration and dependencies. Content is prepared in parallel with design so it does not block build.

PhaseTypical durationWho leadsDeliverable
Scoping1 weekAgency + clientApproved brief, sitemap
UI design2-3 weeksAgencyApproved mockups
Build3-4 weeksAgencyStaging site
ContentIn parallelClientCopy, photos, legals
Review1-2 weeksClient + agencyFixes, sign-off
Total7-11 weeksGo-live

What are the 5 delay causes and how do you avoid them?

Delays almost always come from the same place. Anticipating them turns a 13-week project into an 8-week one.

Delay causeAverage impactHow to avoid it
Content delivered late+2 to 3 weeksContent due before design, contractual deadline
Slow reviews+1 to 2 weeks3-business-day review SLA
Out-of-scope additions+1 to 4 weeksChange-order process, frozen scope
Multiple stakeholders+1 weekA single approver on the client side
Review discovered late+1 to 2 weeksAcceptance criteria written at scoping

Mini case study

Sarah, COO of an engineering firm in Amsterdam, wants to launch her site for a trade show dated 15 March. She contacts the agency on 2 January aiming for 4 weeks: unrealistic. The real plan gives 8 weeks, i.e. go-live on 27 February if content is ready by day 10. She blocks one day to write the copy, names a single approver and sets a one-week buffer. Result: site live on 24 February, three weeks before the show, with no rush surcharge (which would have added 15 to 20 % to the quote).

FAQ

Need a professional website?

Kolonell builds websites that attract clients, optimized for the Sénégalese market. Free quote in 2 minutes.

Prefer a call back?

Leave your WhatsApp number and a Kolonell expert will get back to you within 1 business day. Free, no strings attached.

Can a brochure site ship in 3 weeks?

Yes, but only a template site of 3-4 pages with content already ready, around EUR 3,500-5,000. A custom B2B site of 8-12 pages needs 7 to 11 weeks.

Does rushing cost more?

Yes, an accelerated delivery typically adds 15 to 25 % to the quote to prioritise the team, and raises the risk of errors. Better to plan early.

Who is responsible for content delays?

The client, in 70 % of cases. Contracting a content delivery date and a 3-business-day review SLA protects both parties.

Do you need a buffer in the plan?

Yes, 1 to 2 weeks for a firm launch date. Without a buffer, the smallest review hiccup pushes go-live to the worst possible moment.

When does the clock really start?

At deposit payment and scoping approval, not at quote signature. A project that drags in scoping already starts late.

Let's scope your project. Give us your target date and scope and we will build a realistic 7-11 week plan, indicative budget EUR 8,000-15,000. Detailed quote within 48 h. WhatsApp +221 77 596 93 33.

Tags:#délai création site#planning projet web#phases projet#site Marseille#retard projet#recette site#gestion projet web#timeline site vitrine
Share:

Mohamed Bah

Fondateur, Kolonell

Passionate about digital and entrepreneurship in Africa, Mohamed has been helping Sénégalese businesses with their digital transformation since 2020. Founder of Kolonell, he believes every SME deserves a professional and accessible online présence.