The verdict in three sentences

A web project holds its schedule when the phases are sequenced and client content arrives on time. 2026 ranges: brochure 5-9 weeks, corporate site 10-18 weeks, portal or line-of-business app 4-9 months. The biggest delay risk is not technical: it is the availability of your text, images and sign-offs.

Reference timelines by project type

2026 orders of magnitude for the EU market, with client content delivered on time.

Project typeRealistic timelineCompressed (at risk)
Brochure 5-8 pages5 - 9 weeks3 - 4 weeks
B2B site + blog + SEO8 - 12 weeks6 weeks
Multilingual corporate site10 - 18 weeks8 weeks
E-commerce10 - 16 weeks8 weeks
Portal / client area4 - 7 months3 months
Line-of-business app5 - 9 months4 months

A compressed timeline is not impossible, but it has a price: doubled resources, fewer iterations, or reduced scope.

The key phases of a project

Each phase depends on the previous one. Skipping a step does not save time: it costs more later.

PhaseShare of timelineDeliverable
Framing & RFP10 %Validated scope
UX/UI design25 %Approved mockups
Content (client)ParallelText, images, translations
Development35 %Working site
Content integration15 %Filled pages
QA & testing10 %Fixes, sign-off
Go-live5 %Site in production

The "content" phase is parallel on paper, but in practice it blocks integration if not ready: it is friction point number one.

Factors that stretch the schedule

Knowing these causes lets you neutralise them at framing stage.

Delay causeTypical impactHow to avoid it
Late client content+2 to +6 weeksContent deadline in the RFP
Slow sign-offs+1 to +4 weeksOne decision-maker, 48 h limit
Scope additions+1 to +8 weeksChange orders, v2 backlog
Late multilingual+2 to +5 weeksTranslations from the start
Third-party integrations+1 to +6 weeksAPI access tested early
Insufficient QAGo-live slipPlanned QA, not improvised

The golden rule: every day of client-side sign-off delay pushes the delivery date by at least the same amount.

Need a professional website?

Kolonell builds websites that attract clients, optimized for the Sénégalese market. Free quote in 2 minutes.

Prefer a call back?

Leave your WhatsApp number and a Kolonell expert will get back to you within 1 business day. Free, no strings attached.

Mini case study

Marc, CEO of an industrial mid-cap in Lille, wants his new multilingual corporate site for a trade show in 10 weeks. The realistic timeline is 14 weeks. Two options: compress (doubled resources, +6,000 EUR, quality under strain) or launch a priority version (home, products, contact) in 8 weeks and the rest afterwards. He picks the priority version, makes the show with a credible site, and delivers the remaining 12 pages 5 weeks later. He thus avoids the compression premium and the stress of rushed QA before the event.

FAQ

Why did my project run late when the agency was fast?

In 6 cases out of 10, the cause is client content or slow sign-offs. Development can be on time; if text arrives 3 weeks late, delivery slips by the same amount.

Can we really go faster?

Yes, by cutting scope or doubling resources (+30 to +60 % cost). Compressing without either sacrifices QA, which is paid back in post-launch bugs.

How long does the design phase take?

About 25 % of the project, i.e. 2 to 4 weeks for a B2B site. Endless mockup revisions are the second cause of slippage after content.

Do we have to deliver everything at once?

Not necessarily. A phased go-live (priority pages first) lets you meet a firm deadline like a trade show, then enrich later without pressure.

How do I secure a firm go-live date?

Set the content deadline 3 weeks before go-live, name a single approver, and keep a one-week QA buffer. A date with no QA buffer is a fictional date.

Let's scope your project. Give us your target deadline and scope, and we will propose a realistic schedule with milestones and a content deadline. Detailed quote within 48 h. WhatsApp +221 77 596 93 33.

Tags:#web project timelines#planning#brochure site#line-of-business app#project phases#delay causes#schedule#web quote