Websites10 min read

Late-delivery penalty clauses in a website redesign contract (2026)

Mohamed Bah·Fondateur, Kolonell
October 8, 2026
Share:
Late-delivery penalty clauses in a website redesign contract (2026)

Late-delivery penalty clauses in a website redesign contract (2026)

Websites

The verdict in three sentences

A useful late-delivery penalty sits between 0.5 and 1% of the price per week, capped at 10%, and only works on dated, jointly validated milestones. It is worthless unless the contract also sets the client's obligations (content, approvals, access), because the client causes the delay in six projects out of ten. The real protection lever is a 30/40/30 payment schedule combined with a clear termination clause, far more than the penalty amount.

Penalty levels used in France in 2026

French civil law (article 1231-5 of the Civil Code) lets a judge reduce a manifestly excessive penalty, so a 5% per week clause will rarely be enforced as written. Serious agencies accept a reasonable penalty if it is symmetrical and bounded. Here are 2026 orders of magnitude for a EUR 24,000 (excl. VAT) redesign.

Penalty formulaRateAmount per weekUsual capAgency acceptance
Light penalty0.25% / weekEUR 605% (EUR 1,200)Very good
Standard penalty0.5% / weekEUR 12010% (EUR 2,400)Good
Firm penalty1% / weekEUR 24010% (EUR 2,400)Negotiable
Daily penalty1/1000 per working dayEUR 24 / day10%Good (public tenders)
Heavy penalty2% / weekEUR 48015% (EUR 3,600)Often refused
Uncapped penalty1% / weekEUR 240NoneRefused, risk of judicial reduction

The 10% cap is the balance point: it equals 10 weeks of delay at 1%, after which termination becomes the right answer, not piling up penalties.

Clauses that matter more than the amount

A penalty only triggers on a precise date. If the contract says "delivery expected in spring", there is nothing to penalise. The contract must split the project into milestones, each with its date, deliverable and approval method.

ClauseWhat it setsWhy it is decisiveRecommended wording
Dated milestones4 to 6 stages (mockups, build, acceptance, launch)Makes delay measurableDate + deliverable + approval criterion
30/40/30 schedule30% at order, 40% at acceptance, 30% at launchClient keeps 30% leverageFinal payment after blocking bugs are fixed
Client obligationsContent, logos, access delivered on fixed dates60% of delays come from the clientAutomatic day-for-day date shift
Approval window5 working days per deliverableStops approvals dragging onSilence beyond = tacit approval
Prior formal noticeLetter or email with 8 days to cureTriggering conditionPenalty runs from the notice date
TerminationPossible after 6 to 8 weeks of delayClean exitHandover of code and sources pro rata to sums paid
Force majeureExhaustive list of casesAvoids broad excusesExplicitly exclude subcontractor failure

The most negotiated point is the shift clause. It is fair: if your team delivers copy three weeks late, the launch date moves three weeks. In return, require the agency to alert you in writing from the first day a client deliverable is late, otherwise the shift does not apply.

What a month of delay really costs

The penalty rarely offsets the real loss. If the redesign must support a sales campaign, a trade show or a product launch, the opportunity cost quickly exceeds the contractual cap. For an SME generating 40 quote requests a month through its site, with a 20% conversion rate and an average deal of EUR 6,000, one month of delay on a site expected to double conversions represents roughly EUR 48,000 of potential revenue pushed back. Against that, a EUR 960 penalty (4 weeks at 1%) is symbolic.

The practical consequence is simple: schedule launch six weeks before the commercial event, and make that date an essential contractual milestone whose breach opens the right to terminate.

Mini case study

Need a professional website?

Kolonell builds websites that attract clients, optimized for the Sénégalese market. Free quote in 2 minutes.

Prefer a call back?

Leave your WhatsApp number and a Kolonell expert will get back to you within 1 business day. Free, no strings attached.

Thomas, managing director of an industrial equipment SME in Nantes, signs a EUR 24,000 redesign. He negotiates: 0.75% per week capped at 10%, a 30/40/30 schedule, a day-for-day shift if content arrives late, termination after 8 weeks.

Outcome: the agency delivers acceptance 3 weeks late, 1 of which is down to Thomas's team (product sheets handed over late). The net penalty covers 2 weeks: 2 x EUR 180 = EUR 360, deducted from the EUR 7,200 balance. More importantly, the 30% withheld until launch kept the pressure on: the agency added a developer to finish before the trade show 5 weeks later. Cost of the negotiation: a one-hour meeting.

FAQ

What penalty rate should I propose for a website redesign?

Between 0.5 and 1% of the price per week, capped at 10%. On EUR 24,000, that is EUR 120 to 240 per week and EUR 2,400 at most. Beyond that, the agency will refuse or a judge may reduce the clause.

Can the agency refuse any penalty?

Yes, but it is a signal worth analysing. An agency in control of its schedule usually accepts 0.5% per week if the client-delay shift clause is in the contract. A flat refusal can be offset by a more protective schedule, for example 20/40/40.

What if the delay comes from my own teams?

The shift clause applies: the date moves back by as many days as your delay. In 60% of projects, content is the bottleneck. Appoint an internal content owner and allow 3 to 4 weeks to write 30 pages.

When should I terminate rather than accumulate penalties?

As soon as the 10% cap is reached, about 10 weeks at 1%. The contract must then provide for handover of code, mockups and access pro rata to the sums paid, so another provider can take over without starting from scratch.

Are penalties automatically deductible from the invoice?

Only if the contract says so explicitly, after a formal notice left unanswered for 8 days. Without that wording, you must claim payment separately, which creates a dispute. Provide for set-off against the 30% balance.

Let's scope your project. We price your redesign with a dated milestone plan, a 30/40/30 schedule and written delivery commitments, for an indicative budget of EUR 8,000 to 30,000 depending on scope. Detailed quote within 48 h. WhatsApp +221 77 596 93 33.

Tags:#website redesign contract#late-delivery penalties#web agency contract clauses#SME website redesign#payment milestones#contract negotiation 2026
Share:

Mohamed Bah

Fondateur, Kolonell

Passionate about digital and entrepreneurship in Africa, Mohamed has been helping Sénégalese businesses with their digital transformation since 2020. Founder of Kolonell, he believes every SME deserves a professional and accessible online présence.