The verdict in three sentences
A 40-employee industrial company in Dublin can launch a 10-page brochure site in 6 to 8 weeks, but a site with a product catalogue takes 12 to 20 weeks. With a trade show in 4 months, about 17 weeks, the full catalogue is reachable only if content gathering starts the day the contract is signed, because that is what loses 2 to 4 weeks on average. The safe approach is to launch a first version with the flagship ranges before the show, then expand the catalogue in the following 6 weeks.
Realistic durations by type of site in 2026
| Project type | Pages or product sheets | Realistic timeline | 2026 budget |
|---|---|---|---|
| Simple brochure site | 8 to 10 pages | 6 to 8 weeks | EUR 7,000 to 12,000 |
| Brochure with blog and expertise pages | 15 to 25 pages | 8 to 12 weeks | EUR 10,000 to 16,000 |
| Site with simple catalogue | 50 to 150 products | 12 to 16 weeks | EUR 14,000 to 20,000 |
| Catalogue with technical filters and PDF sheets | 150 to 500 products | 14 to 20 weeks | EUR 18,000 to 25,000 |
| Bilingual catalogue | Any size | +2 to 4 weeks | +15 to 25% |
| ERP or PIM connection | Product sync | +3 to 6 weeks | +EUR 4,000 to 10,000 |
These timelines assume two approval rounds, one decision maker on the client side and content delivered on time. For a laboratory equipment maker, technical sheets (dimensions, standards, certificates, manuals) are often spread across engineering, quality and sales: that is where schedules slip.
Backward schedule for a trade show in 17 weeks
| Weeks | Stage | Deliverable | Who blocks most often |
|---|---|---|---|
| W1 to W2 | Scoping, sitemap, content list | Signed-off specification | Choice of ranges to feature |
| W2 to W6 | Gathering copy, photos, technical sheets | 100% of V1 content | Engineering and quality |
| W3 to W5 | Mock-ups and design | 2 approval rounds | Managing director |
| W5 to W11 | Development, catalogue integration | Site on staging server | Agency |
| W11 to W13 | Product data entry and import | Flagship ranges online | Client and agency |
| W13 to W15 | Acceptance testing, fixes, technical SEO | Signed acceptance | Tester availability |
| W15 to W16 | Go-live, redirects | Site live | DNS and previous supplier |
| W17 | Trade show: QR codes on stand and brochures | Dedicated show pages | Marketing team |
Two rules prevent delays. First, a content delivery deadline written into the contract, with an automatic schedule shift if it is missed. Second, one approver per round: when three directors annotate the same mock-up, a 5-day round becomes 3 weeks.
Plan for external dependencies too. Domain transfer, access to the old host and mapping existing URLs to keep search rankings take 3 to 10 days if the previous supplier is slow. Start these in week 1.
Mini case study
Conor, managing director of a 40-employee laboratory equipment manufacturer near Dublin, wants his site live for a trade show in 17 weeks. His catalogue has 220 products. The agency quote plans 19 weeks for the full bilingual catalogue, at EUR 21,000.
He chooses a V1 with the 60 flagship products, live in week 15, then 160 products added in the 6 weeks after the show. The budget rises to EUR 22,500 with phase 2. At the show, the team expects 300 scanned contacts: if 3% become quote requests averaging EUR 12,000, that is 9 requests and EUR 108,000 of pipeline that a missing site would not have captured.
Need a professional website?
Kolonell builds websites that attract clients, optimized for the Sénégalese market. Free quote in 2 minutes.
FAQ
Can a brochure site be built in under 4 weeks?
Yes for 5 to 6 pages with ready content and an adapted template, but design and SEO stay limited. For 10 custom pages, 6 to 8 weeks is realistic.
How long does content gathering take?
2 to 4 weeks on average for an industrial company, more if technical sheets must be written. Naming an internal owner with 4 to 6 hours a week cuts this in half.
How many approval rounds should we plan?
Two rounds per deliverable (mock-ups, staging) of 3 to 5 working days each. Each extra round adds about a week.
Does a second language extend the schedule?
It adds 2 to 4 weeks for a technical catalogue, because terminology must be checked by an engineer. Allow EUR 0.10 to 0.18 per word for professional technical translation.
What happens if we deliver content late?
A well-drafted contract moves the go-live date by the same amount and suspends agency penalties. That is why a reduced V1 makes sense when an event sets the date.
Let's scope your project. Give us your deadline and number of products: we build a realistic backward schedule with V1 scope, indicative budget and the duration of each stage. Detailed quote within 48 h. WhatsApp +221 77 596 93 33.