The verdict in three sentences
Fixed price fits when scope is stable and documented, but you pay a 15 to 25% risk premium built into the price. Time and materials (T&M) is cheaper per day but shifts overrun risk to the buyer. For most SMBs in 2026, the best compromise is capped T&M split into 6 to 8 week lots, with a delivery commitment per lot.
2026 day rates: what a day costs in London
Before choosing a contract model, you need the price of a day. The ranges below are 2026 orders of magnitude seen in the London market (contractors, agencies and consultancies), excluding VAT and expenses.
| Profile | Contractor day rate | Agency or consultancy day rate | Typical share of a project |
|---|---|---|---|
| Mid-level developer (3 to 5 years) | 500 to 650 GBP | 600 to 750 GBP | 50 to 60% |
| Senior developer or lead | 650 to 800 GBP | 750 to 950 GBP | 10 to 20% |
| Project manager or product owner | 550 to 750 GBP | 700 to 900 GBP | 10 to 15% |
| UX/UI designer | 450 to 650 GBP | 550 to 750 GBP | 5 to 10% |
| QA tester | 350 to 500 GBP | 450 to 600 GBP | 5 to 10% |
| Architect or DevOps | 700 to 900 GBP | 800 to 1,100 GBP | 5% |
A 120 person-day project at a weighted average of 680 GBP therefore represents about 81,600 GBP on T&M, before any overrun.
Fixed price, T&M, capped T&M: who carries the risk?
| Criterion | Fixed price | Pure T&M | Capped T&M per lot |
|---|---|---|---|
| Price for 120 estimated days | 94,000 to 102,000 GBP (15 to 25% premium) | 81,600 GBP if no overrun | 81,600 GBP, capped at 90,000 GBP |
| Who carries overrun risk | Vendor | Client | Shared |
| Scope flexibility | Low, paid change requests | Full | Good, decided at each lot |
| Prerequisite | Detailed requirements | Active client steering | Prioritised backlog per lot |
| Overrun seen in practice | Change requests: 10 to 30% | 20 to 50% without steering | 0 to 10% |
| Main legal risk | Scope dispute | IR35 status for contractors | Low if deliverables are defined |
Fixed price remains relevant for a tightly scoped first lot (prototypes, a 6-week MVP). Pure T&M makes sense when the client team can steer a backlog daily. In the UK, when you hire individual contractors on T&M through their own limited company, IR35 off-payroll rules apply: medium and large clients must issue a status determination, and a contractor deemed "inside IR35" costs more once employer contributions are added. Buying from an agency on deliverables usually sidesteps this.
Splitting into 6 to 8 week lots
A 6 to 8 week lot equals 3 or 4 two-week sprints. At the end of each lot, the buyer signs off acceptance, pays for the lot and decides what comes next. This limits financial exposure: you are never committed beyond one lot, about 27,000 to 30,000 GBP per lot for a 120-day project split into 3 lots.
Put in the contract: the cap per lot, the overrun clause (beyond the cap, the vendor finishes at its own cost or at a 50% reduced rate), and acceptance criteria per lot.
Mini case study
Need a professional website?
Kolonell builds websites that attract clients, optimized for the Sénégalese market. Free quote in 2 minutes.
Tom, IT procurement lead at a London retail group, must buy a returns management app estimated at 120 person-days. Fixed-price offer: 99,000 GBP. T&M offer: 81,600 GBP estimated, uncapped. He negotiates capped T&M in 3 lots, overall cap 90,000 GBP, overrun billed at 50%. Illustrative example: the project uses 128 days, or 87,040 GBP, under the cap. Saving versus fixed price: 11,960 GBP, about 12%, with the ability to rebalance scope at each lot.
FAQ
What is a typical developer day rate in London in 2026?
For a mid-level developer, expect 500 to 650 GBP as a contractor and 600 to 750 GBP through an agency. Seniors and leads range from 650 to 950 GBP depending on the supplier.
Why is fixed price more expensive than T&M?
The vendor builds in a 15 to 25% risk premium to cover the unknown. If scope is well described, that premium buys peace of mind; if it is vague, you will pay change requests on top.
What is capped time and materials?
It is T&M with a maximum amount per lot or per project. Beyond the cap, the vendor finishes at its own cost or at a reduced rate, sharing the risk while keeping flexibility.
How long should a lot be?
6 to 8 weeks, or 3 to 4 sprints. That limits the commitment to roughly 27,000 to 30,000 GBP per lot for a 120-day project and gives a regular decision point.
Does IR35 affect my choice?
Yes, if you engage individual contractors on T&M, you must assess their IR35 status, and an inside-IR35 determination raises the real cost. Contracting an agency on defined deliverables keeps the risk with the supplier.
Let's scope your project. Tell us about your application: we propose a lot-based plan with a cap, an indicative budget (custom applications from 2,500,000 to 15,000,000+ FCFA, about 3,810 to 22,870+ EUR depending on complexity) and a timeline per lot. Detailed quote within 48 h. WhatsApp +221 77 596 93 33.
Mohamed Bah
Fondateur, Kolonell
Passionate about digital and entrepreneurship in Africa, Mohamed has been helping Sénégalese businesses with their digital transformation since 2020. Founder of Kolonell, he believes every SME deserves a professional and accessible online présence.