Digital Africa11 min read

Project Management Software for Engineering Consultancies in London: Cost

Mohamed Bah·Fondateur, Kolonell
October 15, 2026
Share:
Project Management Software for Engineering Consultancies in London: Cost

Project Management Software for Engineering Consultancies in London: Cost

Digital Africa

The verdict in three sentences

A 30-engineer consultancy that does not measure margin per project discovers overruns at close-out, when it is too late to renegotiate. A sector ERP at EUR 80-150 per user per month provides a standard framework, while a custom tool at EUR 35,000-80,000 (about USD 38,000-88,000) follows your work stages (concept, scheme, detailed design, construction) and your progress billing logic. Firms that track time by stage recover about 3 points of margin in the first year.

Sector ERP or custom tool: 2026 prices

Engineering ERP vendors offer project, time and billing modules. They suit firms that accept their structure. Consultancies mixing design, expert witness and coordination work often hit their limits. Here are 2026 orders of magnitude for 30 users, whether in Marseille or London (excluding VAT).

OptionUpfront costAnnual cost (30 users)TimelineFit with work stages
Engineering sector ERPEUR 8,000 to 20,000 setupEUR 28,800 to 54,0003 to 6 monthsMedium
Generic project management toolEUR 1,000 to 3,000EUR 5,400 to 10,8001 monthLow, no margin per project
Custom tool (time, margin, billing)EUR 35,000 to 55,000EUR 4,000 to 7,0004 to 5 monthsFull
Full custom tool (resourcing, subcontracting, BI)EUR 55,000 to 80,000EUR 6,000 to 10,0006 to 8 monthsFull
Status quo spreadsheetsEUR 0Hidden cost: unmanaged marginImmediateNone

Over five years, the sector ERP costs EUR 152,000 to 290,000, the custom tool EUR 55,000 to 130,000. The gap easily funds a serious specification and ongoing maintenance.

The indicators that make margin visible

The tool must link three flows: hours logged per stage, contracted fees and invoices issued. Without that link, you cannot tell whether a EUR 120,000 project has used 70 % of its hours budget for 40 % progress.

IndicatorCalculationSuggested alert thresholdDecision triggered
Hours budget consumed per stageActual hours / sold hoursAbove 80 % before stage endVariation or reallocation
Margin per projectFees minus loaded hour cost and subcontractingBelow 15 %Review with project lead
Work in progress unbilledValidated progress minus invoicedAbove EUR 20,000Issue progress invoice
Billable utilisationBillable hours / total hoursBelow 70 %Revisit resourcing plan
Average collection timeDays between invoice and paymentAbove 60 daysChase, contract terms
Subcontracting costShare of fees paid outAbove 25 %In-house or external choice

Progress billing generated from the tool also reduces unbilled work: in equipped consultancies it often falls by 30 to 40 %.

Mini case study

James, managing director of a 30-engineer structural consultancy in London, turns over EUR 3.2 million with a 6 % net margin. His refurbishment projects regularly overrun during construction stage without anyone noticing before close-out.

He invests EUR 62,000 in a custom tool (time by stage, margin per project, progress billing), plus EUR 7,500 per year of maintenance. By spotting overruns at 80 % of the hours budget, he triggers variations on 9 projects and reallocates two engineers. Gain: 3 points of margin, or EUR 96,000 per year. Payback comes in about 8 months.

Need a professional website?

Kolonell builds websites that attract clients, optimized for the Sénégalese market. Free quote in 2 minutes.

Prefer a call back?

Leave your WhatsApp number and a Kolonell expert will get back to you within 1 business day. Free, no strings attached.

You are :

FAQ

Will our engineers actually log their time?

Yes, if logging takes under 5 minutes a day from mobile or desktop, with projects and stages pre-filled. Completion rates then exceed 90 % from the second month.

Can the tool pull our accounting data?

Yes, through an export or API with your accounting software. This integration usually accounts for EUR 5,000 to 10,000 of the budget.

How long until the tool is live?

Allow 4 to 5 months for time, margin and billing, then 2 to 3 more months for resourcing and BI if you add them.

Is an off-the-shelf ERP not less risky?

It is on maintenance, but 30 users at EUR 80-150 per month means EUR 28,800 to 54,000 every year. If your stages and billing methods are non-standard, configuration quickly exceeds EUR 20,000.

Can we start small?

Yes, a first phase at EUR 35,000 focused on time by stage and margin per project often pays for the rest.

Let's scope your project. Send us your headcount, project types and current tools, and we will price a custom project management tool between EUR 35,000 and 80,000, delivered in 4 to 8 months. Detailed quote within 48 h. WhatsApp +221 77 596 93 33.

Tags:#engineering consultancy#project management#project profitability#custom software#London#progress billing