Real corporate website rebuild timeline in Amsterdam in 2026: week by week

Mohamed Bah·Fondateur, Kolonell
October 11, 2026
Share:
Real corporate website rebuild timeline in Amsterdam in 2026: week by week

Real corporate website rebuild timeline in Amsterdam in 2026: week by week

Websites

The verdict in three sentences

A bilingual Dutch and English corporate site for a group with several subsidiaries takes 14 weeks in a realistic scenario, within a range of 10 to 20 weeks. The timeline depends less on the agency than on multi-entity sign-off and on content and translation, which together sit on the critical path. Announce a launch date built on the realistic scenario plus two weeks of buffer and you will not have to move it.

The week-by-week plan

This plan fits a 30-page bilingual site for a group of 300 to 1,000 staff with three to five subsidiaries, at 20,000 to 55,000 EUR excluding VAT. Durations are 2026 estimates.

WeeksPhaseDeliverableWho signs offMinimum / realistic / risky
W1 to W3Discovery: workshops, sitemap, goalsDiscovery brief and sitemapGroup comms + board2 / 3 / 4 weeks
W3 to W5Wireframes and user journeysWireframes for 6 to 8 templatesGroup comms + subsidiary leads1 / 2 / 3 weeks
W5 to W7Visual designHome page and key templatesBoard2 / 2 / 4 weeks
W4 to W10Dutch content writing (parallel)30 pages approvedBusiness units3 / 6 / 9 weeks
W8 to W11English translation and review30 pages in EnglishGroup comms2 / 2 / 3 weeks
W7 to W11Build and CMS setupStaging siteGroup comms + IT3 / 4 / 5 weeks
W12 to W13Content entry, redirects, accessibility checkComplete staging siteGroup comms1 / 1 / 2 weeks
W13 to W14Acceptance testing and go-liveSign-off report, editor trainingGroup comms + IT1 / 1 / 2 weeks

Because several phases overlap, the minimum totals 10 weeks, realistic 14 and risky 20.

The delays that hit most often

CauseTypical delayFrequencyCountermeasure
Subsidiary content arrives late2 to 6 weeksVery commonOne content owner per page, shared deadline sheet
Board or subsidiary sign-off slips1 to 3 weeksCommonSign-off slots booked in week 1
Translation started after Dutch is final2 to 3 weeksCommonTranslate per page as soon as it is approved
Scope added mid-project1 to 4 weeksCommonPhase 2 backlog after launch
Cookie and privacy review by legal1 to 2 weeksOccasionalSend to legal in week 9
DNS or hosting access missing3 to 10 daysOccasionalAccess inventory in week 1

Content is the true critical path: 30 pages at 2 hours of writing and 1 hour of review is 90 hours, spread across busy managers in several entities. Dutch rules on cookies, enforced by the Autoriteit Persoonsgegevens, mean consent must be in place before analytics fire, so plan legal review early.

How to hold the date you announce

Appoint an internal project lead with at least 20 % of their time, book sign-off dates in discovery with a maximum of 5 working days per feedback round, and cap approvers at three per deliverable. Treat each subsidiary as a stakeholder with one representative, not as an extra approval layer. Government-related entities should also check the Dutch digital accessibility requirements, based on WCAG 2.1 AA.

Mini case study

Illustrative example: Eva, head of communications at an Amsterdam-based logistics and services group with 600 staff and four subsidiaries. The board wants the new site live before a sector event in late June. The project starts on 2 February with a 38,000 EUR budget and 34 pages.

Need a professional website?

Kolonell builds websites that attract clients, optimized for the Sénégalese market. Free quote in 2 minutes.

Prefer a call back?

Leave your WhatsApp number and a Kolonell expert will get back to you within 1 business day. Free, no strings attached.

You are :

Realistic plan: 14 weeks, launch on 11 May. With two weeks of buffer, Eva announces 25 May. Two subsidiaries hand in copy three weeks late, partly absorbed by translating page by page: the site goes live on 27 May, two days after the announced date and four weeks before the event. Each week of delay avoided saves roughly 1,500 EUR of agency and internal coordination time.

FAQ

How long does a corporate website rebuild take in Amsterdam in 2026?

Ten to 20 weeks, with 14 weeks realistic for a 30-page bilingual site. Groups with more than five subsidiaries or three languages often exceed 18 weeks.

Should translation wait for the final Dutch copy?

No, translate each page once it is approved. This saves 2 to 3 weeks on a 30-page site.

How many approval rounds should we plan?

Two per deliverable, each of 1 to 2 weeks. Beyond three approvers, add a week per round.

What does professional copywriting cost?

In the Netherlands, 200 to 450 EUR per page for Dutch copy, plus 0.12 to 0.20 EUR per word for translation. It shortens the critical path by several weeks.

How long should acceptance testing take?

One week for 30 pages, with a shared issue log. Blocking bugs should be fixed within 48 hours.

Let's scope your project. Tell us your page count, approvers and target date, and we will send back a priced, week-by-week plan. Detailed quote within 48 h. WhatsApp +221 77 596 93 33.

Tags:#website rebuild timeline#Amsterdam corporate website#web project plan#website redesign#website development#delivery timelines#Amsterdam
Share:

Mohamed Bah

Fondateur, Kolonell

Passionate about digital and entrepreneurship in Africa, Mohamed has been helping Sénégalese businesses with their digital transformation since 2020. Founder of Kolonell, he believes every SME deserves a professional and accessible online présence.